Short Haul, High Stakes: BESS & PCS Storage + Final Mile Delivery
- Jun 24
- 1 min read
Updated: Jun 29
Supporting utility-scale energy deployment through long-term storage, coordinated sequencing, and high-volume final mile execution.

Project Overview
One Source Freight Solutions supported a utility-scale energy project with seven months of secure storage and final mile delivery of 225 oversized BESS and PCS units.
Inventory was strategically staged near the project site in Salt Lake City to reduce transportation costs and support rapid deployment once installation activities began.
Over a 21-day delivery window, OSFS coordinated transport in a strict 4:1 BESS-to-PCS sequence aligned to onsite crane and installation schedules.
Challenges
Managing Oversized Equipment Storage
Units exceeding 80,000 lbs.
Large storage footprint requiring organized staging lanes
Ground preparation requirements to support unit weight
Long-term inventory management over a seven-month period
Maintaining High-Volume Delivery Flow
15 loads per day required during peak operations
Two-turn-per-day routing strategy needed
Strict 4:1 BESS-to-PCS sequencing requirements
Continuous coordination between carriers and onsite teams
Our Solution
Storage Operations
Facilitated site preparation and ground reinforcement to support long-term storage of overweight units
Configured staging areas for efficient oversized equipment movement
Positioned inventory near the project site to reduce final mile transportation costs
Supported onsite testing and preparation before deployment
Final Mile Transportation
Designed a delivery strategy optimized for continuous truck utilization
Provided dedicated project management team to maintain delivery coordination and schedule adherence
Maintained strict 4:1 BESS-to-PCS delivery sequencing
Deployed multi-axle step decks and RGNs matched to unit dimensions and weight
Sustained 15 loads per day with zero transportation delays
Results
Zero Delays
Full 21-day schedule completed without interruption
Coordinated Execution
Continuous truck flow maintained across all stakeholders
High Throughput
Sustained up to 15 deliveries per day
Sequence Integrity
All deliveries maintained required 4:1 order

_edited.png)