Three phases of high-volume freight to a remote site, with each new phase awarded on the strength of the one before it
The complication
Rural road weight limits, narrow access and strict municipal routing in phase one. Heavy rain and a ten-day weather shutdown in phase two. Twenty-four-hour factory release notice and tight coordination in phase three. Each phase was awarded only on the performance of the one before.
What we did
Custom driver instructions and pre-trip route planning. Hold-and-release deliveries with freight diverted to yards during the shutdown, coordinated daily with the site. Forecast-based carrier planning to meet 24-hour releases. Deliveries stayed in sequence through all three phases.